What is the schedule for the project?
- Submit the Draft Environmental Impact Statement to the Federal
Railroad Administration -- September 2003
- Hold a Public Hearing on the Draft Environmental Impact Statement
– December 2003
- Complete the Final Environmental Impact Statement and secure
Record of Decision -- 2004
- U.S. Congress makes determination on whether the Baltimore-Washington
or Pittsburgh project receives funding for Final Design and Construction
- 2004 or 2005
- Maryland appropriates matching funds and creates an ownership
entity
- Solicit and award contract for design, build, operation and
maintenance (DBOM)
- Final Design and Construction -- 2005-2009
- Testing -- 2009-2010
- Revenue Service -- 2010
(This schedule assumes there are no delays obtaining project approvals
or funding.)
|